Three Week Look-Ahead 4/17/20 - 5/8/20

3 months ago

Below is your three week look-ahead for 4/17 - 5/8

Update as of 4/29/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled.
  • Construction of the bridge has begun. So far, 6 of the 12 drilled underground shafts have been completed. Six more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic has been shifted to the south side of the roadway.Work has started along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 8 a.m. to 5 p.m.

CLOSURE NOTICE: Issaquah Fall City Road is closed for construction.

  • Local access will be maintained during the closure.
  • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.
  • For more information and project updates please visit the project portal on Connect Sammamish.


Update as of 4/24/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled.
  • Construction of the bridge has begun. So far, two of the drilled underground shafts have been completed. Ten more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic is expected to be shifted to the south side of the roadway within the next two weeks.
  • The contractor will continue to work along the south side of the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Update as of 4/17/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Remaining work is expected to be completed on Monday, April 20th.
  • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
  • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving started on Friday, April 17 and is scheduled to be completed during the week of April 20th.
  • Starting Monday, April 20th, the bridge between 247th Ave SE and Klahanie Dr SE will begin. The drillers will be mobilizing on site and start drilling the concrete bridge columns. The area will be fenced off from the public.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 8 a.m. to 5 p.m.

CLOSURE NOTICE:

Issaquah Fall City Road closed for construction.

  • Local access will be maintained during the closure.
  • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.