Three Week Look-Ahead 3/6/20-3/27/20

4 months ago


Below is your three week look-ahead for 3/6/20-3/27/20


Update as of 3/27/20

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th and 247th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

DATES

Estimated dates for the ROAD CLOSURE are April 13, 2020, to December 31, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.


Update as of 3/13/20

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th and 247th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Update as of 3/6/20

  • Puget Sound Energy (PSE) will be working this Saturday, 3/7, from 9 a.m. to 6 p.m. along the south side of Issaquah-Fall City Road between 247th and Klahanie Blvd. They will be trimming trees to help set new power poles.
  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
    • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
    • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road(External link),may result in shorter drive times.

DATES

  • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
  • August 2021 - END CONSTRUCTION