Road Projects for Week of February 13 - 19, 2021
The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.
SE 43rd Way and Providence Point Signal
This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.
Issaquah Fall City Road
Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.
- PSE Gas main installation under bridge continues for approximately 2 more weeks.
- Storm sewer and water main installation under bridge continues.
- Sidewalk construction on north side of bridge is completed.
- Barrier on the south side of bridge is being formed.
- Concrete work continues over next 2 weeks for medians, stamped concrete, and remaining sidewalks, followed by road grade preparation for paving.
- Trenching continues to bring power to streetlights.
- See new construction photos uploaded to the project page.
Please visit Issaquah Fall City Road Phase 1 Construction Updates on Connect Sammamish for full project updates.
Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.