Know before you go. Make sure there aren't any unexpected delays in your drive by checking the weekly News Feed below for scheduled work project in Sammamish.

Please Note: Schedules may change due to weather and/or equipment availability.


Know before you go. Make sure there aren't any unexpected delays in your drive by checking the weekly News Feed below for scheduled work project in Sammamish.

Please Note: Schedules may change due to weather and/or equipment availability.

  • Road Projects for Week of April 3-8, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
    2. Remaining finish paving on the other side of project is planned for next dry weather.
    3. Utilities will be raising access lids in finished paved areas.
    4. Final bridge barrier section is nearly done.
    5. Guardrail and fence installation are underway.
    6. Topsoil and plants will be placed in roadway areas.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 27- April 2, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped.
    2. Remaining finish paving on the other side of project is planned for next dry weather.
    3. Utilities will be raising access lids in finished paved areas.
    4. Final bridge barrier section is nearly done.
    5. Guardrail and fence installation are underway.
    6. Topsoil and plants will be placed in roadway areas.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 20 - 26, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
    2. Remaining finish paving on the other side of project is planned for next dry weather.
    3. Utilities will be raising access lids in finished paved areas.
    4. Final bridge barrier section is nearly done.
    5. Guardrail and fence installation are underway.
    6. Topsoil and plants will be placed in roadway areas.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 13 - 19, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Paving operations begin March 15 on the west end of the corridor between Eastridge Church and 247th PL SE (7 am – 5 pm).
    2. Expect delays up to 30-minutes during paving operations. Please plan accordingly.
    3. Duration – approximately 3 weeks.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 6 - 12, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    228th Avenue SE near SE 16th Street (March 8 – March 10)

    The City of Sammamish will be conducting catch basin apron repair on northbound 228th Avenue SE near SE 16th St (water district entrance). The repair preparation work is scheduled for Monday, March 8 and the contractor will be back Wednesday, March 10 to pour concrete. Northbound traffic will be reduced to one lane around the small work zone area. Construction hours are 8am to 4pm.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Paving is scheduled to begin March 15, weather permitting.
    2. PSE Gas Crews will complete trench work near the bridge by March 8, then continue with installation under the bridge while paving is underway.
    3. Bridge barrier placement continues.
    4. Remaining areas of sidewalk, curb, and gutter continues.
    5. Roundabout stamped concrete truck aprons are poured.
    6. Fencing will begin this week.
    7. Landscaping – topsoil placement ongoing and planting to begin soon.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of February 27 - March 5, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Bridge traffic barrier pour – first section has cured, and forms have been stripped. Work continues on remaining sections.
    2. Moment slabs supporting traffic barriers at the bridge approaches are completed. Sidewalks are now being formed atop these.
    3. Sidewalk grading underway in remaining areas.
    4. PSE Gas crews continue to install gas main under the bridge.
    5. Roundabouts – prepping for curb installation and truck aprons.
    6. Landscaping – installing topsoil behind sidewalks
    7. Fence installation beginning soon.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of February 20 - 26, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times. Your safety is paramount,

    1. Bridge barrier pour scheduled this week on the south side of the bridge.
    2. Moment slab rebar is being installed now at the bridge approach, and the last segment will soon be poured.
    3. PSE Gas continues to install utilities under the bridge.
    4. Curb installation at splitter island and median islands underway.
    5. Roundabout truck aprons at 242nd and SE Klahanie Drive are being constructed.
    6. Roundabout landscape preparation is underway.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of February 13 - 19, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    1. PSE Gas main installation under bridge continues for approximately 2 more weeks.
    2. Storm sewer and water main installation under bridge continues.
    3. Sidewalk construction on north side of bridge is completed.
    4. Barrier on the south side of bridge is being formed.
    5. Concrete work continues over next 2 weeks for medians, stamped concrete, and remaining sidewalks, followed by road grade preparation for paving.
    6. Trenching continues to bring power to streetlights.
    7. See new construction photos uploaded to the project page.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of February 6 - 12, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    Intersection Traffic Lights Maintenance

    The City is performing maintenance on intersection traffic lights throughout the city. Lights my flash for short periods, and possibly go dark for short periods. This work will occur intermittently throughout the day.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    1. Utility installation under the bridge – dry utilities have been completed, with water main and storm sewer installation now underway.
    2. Bridge barrier concrete pour scheduled for next week.
    3. PSE Gas utility relocation (by third party) continues within the bridge approaches.
    4. A new pedestrian crossing signal (HAWKS) at the Pacific Cascade Middle School entrance is now activated, and streetlights are being wired for power.
    5. Base paving done at intersections of 242nd, 247th, and Klahanie Drive SE, opening roundabouts for circulation.
    6. The large new detention pond at Klahanie Drive SE has been completed and is now collecting stormwater.
    7. Curbs and gutters for roundabouts and median islands will be installed over the next two weeks.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of January 30 - February 5, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    Intersection Traffic Lights Maintenance

    Through the month of January, the City will be performing maintenance on intersection traffic lights throughout the city. Lights my flash for short periods, and possibly go dark for short periods. This work will occur intermittently throughout the day.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)

    Issaquah Fall City Road Update:

    Due to unforeseen circumstances, including construction delays caused by necessary third party utility relocations and inclement weather, the City of Sammamish Public Works Department has determined the road opening by end of January is not feasible.

    The City of Sammamish has looked at options to hasten the construction or partial openings, but has determined in an abundance of caution that these options are not safe nor realistic due to weather events and fiscal constraints.

    Upon reviewing the contractor's updated and current schedule, and the status of utility relocations, the bridge and roadway are now scheduled to be opened to traffic on May 1, 2021.

    We understand and apologize for this inconvenience and thank you for your continued patience as we work to improve the City’s traffic flow.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates on Connect Sammamish.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.