  • Road Projects for the Week of May 1 - 7, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Speed Limit Reinstated to 35 mph on 212th Ave SE effective May 3rd, 2021

    The speed limit on 212th Ave SE between SE 12th Street and SE 18th Street will be reinstated to 35 mph effective May 3rd, 2021. Heavy rains in February of 2020 caused flooding of Ebright Creek which expedited the erosion of the gabion wall supporting the roadway. In the summer of 2020 out of an abundance of caution, the speed limit was reduced from 35 mph to 25 mph to reduce any excess forces or vibration that might expedite the erosion of the subgrade. The City hired a Geotechnical Engineer that produced a report and concluded that the difference in the speed limit between 25 mph and 35 mph does not significantly increase the rate of decay or erosion of the roadway subgrade. Therefore, the speed limit will be reinstated to 35 mph effective May 3rd, 2021. This area will continue to require observation and maintenance until a permanent solution can be assessed and implemented.

    Ebright Creek Fish Passage Project Construction starting in June

    Beginning in June this project will start construction to restore the Ebright Creek crossing at East Lake Sammamish Parkway. The project will remove the existing culvert pipes and replace them with a fully fish passable box culvert, with the goals of improving stream habitat and fish passage to support Kokanee salmon and other fish species. Most of the work is anticipated to be complete by September 2021. During construction, drivers can expect intermittent lane closures to allow for utility relocation and site preparation. Later this summer there will be up to a 3 week closure of East Lake Sammamish Parkway at Ebright Creek to allow for installation of the box culvert. Additional notifications, message boards, and signs will be posted to detour traffic around the closure. Please visit the project page on Connect Sammamish to learn more.

    NE 8th Street natural gas main replacement

    Starting 4/27, PSE and IFS crews will be replacing a portion of the existing underground natural gas main through a portion of NE 8th St and 228th Ave NE near the intersection of 228th Avenue NE and Inglewood Hill Road / NE 8th Street. Work is expected to last two weeks with work hours typically Monday-Friday 9 a.m. to 4 p.m. Throughout the work zone, there will be lane revisions with signs and traffic control flaggers guiding traffic. Street parking will be limited near the project area.

    228th Avenue Curb Ramp Retrofit and Catch Basin Repairs

    Starting May 3rd, the City of Sammamish’s contractor will begin road work on 228th Avenue to retrofit curb ramps, install concrete catch basin aprons and install irrigation sleeve crossings from SE 8th St to NE 8th St. This work is in preparation for the City resurfacing 228th Avenue in 2022 and benefits the City’s ADA Transition Plan goal of retrofitting all public facilities to meet the current Americans with Disabilities Act (ADA) standards. Lane closure hours through the work zone will be between 8:00 a.m. and 4:00 p.m. Monday through Friday. Traffic will be merged to one lane through the work zone and steel plates are anticipated to be on the roadway overnight.

    Issaquah Fall City Road

    The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
    • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

    Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)

    Improvements at East Lake Sammamish Parkway and SE 43rd Way Roundabout

    This is a City of Issaquah project. The City of Issaquah is planning summer road improvements work at East Lake Sammamish Parkway and SE 43rd Way Roundabout. The project intends to improve safety for all road users, increase visibility, and facilitate pedestrian movement at the intersection. More information will be posted as we receive it.

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

  • Road Projects for the Week of April 24 - 30, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    NE 8th Street natural gas main replacement

    Starting 4/27, PSE and IFS crews will be replacing a portion of the existing underground natural gas main through a portion of NE 8th St and 228th Ave NE near the intersection of 228th Avenue NE and Inglewood Hill Road / NE 8th Street. Work is expected to last two weeks with work hours typically Monday-Friday 9 a.m. to 4 p.m. Throughout the work zone, there will be lane revisions with signs and traffic control flaggers guiding traffic. Street parking will be limited near the project area.

    Pavement activity on SE 8th St.

    Pavement activity on SE 8th Street between 214th Ave SE and 218th Ave SE and along 218th Ave SE north of SE 8th Street begun in preparation for new asphalt placement. One lane will be open through the day, and two lanes will be open at night with flaggers directing traffic. Work is scheduled to be finished Friday 4/23 but is subject to change.

    228th Avenue Curb Ramp Retrofit and Catch Basin Repairs

    Starting May 3rd, the City of Sammamish’s contractor will begin road work on 228th Avenue to retrofit curb ramps, install concrete catch basin aprons and install irrigation sleeve crossings from SE 8th St to NE 8th . This work is in preparation for the City resurfacing 228th Avenue in 2022 and benefits the City’s ADA Transition Plan goal of retrofitting all public facilities to meet the current Americans with Disabilities Act (ADA) standards. Lane closure hours through the work zone will be between 8:00am and 4:00pm Monday through Friday. Traffic will be merged to one lane through the work zone and steel plates are anticipated to be on the roadway overnight.

    Issaquah Fall City Road

    The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 PM on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
    • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

    Daytime project work hours are 7:30 AM - 5:00 PM, Saturday work hours: 9:00 AM - 6:00 PM

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.

    Improvements at East Lake Sammamish Parkway and SE 43rd Way Roundabout

    This is a City of Issaquah project. The City of Issaquah is planning summer road improvements work at East Lake Sammamish Parkway and SE 43rd Way Roundabout. The project intends to improve safety for all road users, increase visibility, and facilitate pedestrian movement at the intersection. More information will be posted as we receive it.

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.


  • Road Projects for the Week of April 17 - 23, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Update as of 4/20:

    Pavement activity on SE 8th Street between 214th Ave SE and 218th Ave SE and along 218th Ave SE north of SE 8th Street has begun in preparation for new asphalt placement. One lane will be open through the day, and two lanes will be open at night with flaggers directing traffic. Work is scheduled to be finished Friday 4/23 but is subject to change.



    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    The closure between 247th Place SE and Klahanie Dr. SE will open at 2:30 PM on April 16, 2021.

    There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements.

    *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    • At 2:30 PM, Friday April 16th, the roadway will open up to the public between 247th PL SE and Klahanie. During work hours the public will encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
    • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

    Daytime project work hours are 7:30 AM - 5:00 PM, Saturday work hours: 9:00 AM - 6:00 PM

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.


  • Road Projects for Week of April 9-16, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

    *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    • By end of shift Friday, April 9th, the contractor will have removed barrels from the roadway between 240th and 247th. The public will have full use of the roadway (both lanes in both directions) during off-hour times. During work hours the public will encounter short term (day time) lane closures as necessary to complete punchlist work. The significant item of work to be completed after this week is sidewalk in front of the Issaquah Montessori; this is waiting for Utility Companies work to raise their vault lids.
    • By end of shift Friday April 16th, the roadway will open up to the public between 247th PL SE and Klahanie. During work hours the public will encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
    • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of April 3-8, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
    2. Remaining finish paving on the other side of project is planned for next dry weather.
    3. Utilities will be raising access lids in finished paved areas.
    4. Final bridge barrier section is nearly done.
    5. Guardrail and fence installation are underway.
    6. Topsoil and plants will be placed in roadway areas.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 27- April 2, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped.
    2. Remaining finish paving on the other side of project is planned for next dry weather.
    3. Utilities will be raising access lids in finished paved areas.
    4. Final bridge barrier section is nearly done.
    5. Guardrail and fence installation are underway.
    6. Topsoil and plants will be placed in roadway areas.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 20 - 26, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)(External link)

    Downtown Redmond Link Extension (DRLE)

    This is a City of Redmond project. To learn more about this project, please visit the DRLE tab in Cone Zone.

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
    2. Remaining finish paving on the other side of project is planned for next dry weather.
    3. Utilities will be raising access lids in finished paved areas.
    4. Final bridge barrier section is nearly done.
    5. Guardrail and fence installation are underway.
    6. Topsoil and plants will be placed in roadway areas.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 13 - 19, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Paving operations begin March 15 on the west end of the corridor between Eastridge Church and 247th PL SE (7 am – 5 pm).
    2. Expect delays up to 30-minutes during paving operations. Please plan accordingly.
    3. Duration – approximately 3 weeks.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of March 6 - 12, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    228th Avenue SE near SE 16th Street (March 8 – March 10)

    The City of Sammamish will be conducting catch basin apron repair on northbound 228th Avenue SE near SE 16th St (water district entrance). The repair preparation work is scheduled for Monday, March 8 and the contractor will be back Wednesday, March 10 to pour concrete. Northbound traffic will be reduced to one lane around the small work zone area. Construction hours are 8am to 4pm.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Paving is scheduled to begin March 15, weather permitting.
    2. PSE Gas Crews will complete trench work near the bridge by March 8, then continue with installation under the bridge while paving is underway.
    3. Bridge barrier placement continues.
    4. Remaining areas of sidewalk, curb, and gutter continues.
    5. Roundabout stamped concrete truck aprons are poured.
    6. Fencing will begin this week.
    7. Landscaping – topsoil placement ongoing and planting to begin soon.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

  • Road Projects for Week of February 27 - March 5, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The following road work projects are scheduled in Sammamish for this week. Schedules may change due to weather and/or equipment availability.

    SE 43rd Way and Providence Point Signal

    This is a City of Issaquah project. To sign up for project updates and traffic alerts, please visit https://issaquahwa.gov/3130/SE-43rd-Way-Signal.(External link)

    Issaquah Fall City Road

    Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

    *Safety Reminder* – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

    1. Bridge traffic barrier pour – first section has cured, and forms have been stripped. Work continues on remaining sections.
    2. Moment slabs supporting traffic barriers at the bridge approaches are completed. Sidewalks are now being formed atop these.
    3. Sidewalk grading underway in remaining areas.
    4. PSE Gas crews continue to install gas main under the bridge.
    5. Roundabouts – prepping for curb installation and truck aprons.
    6. Landscaping – installing topsoil behind sidewalks
    7. Fence installation beginning soon.

    Please visit Issaquah Fall City Road Phase 1 Construction Updates and its Three-week look-ahead on Connect Sammamish for full project updates.

    Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.