Three Week Look-ahead 11/27 - 12/18

Below is your three week look-ahead for 11/27 - 12/18:

Update as of 12/18:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume in early December, as the utilities complete the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.



Update as of 12/4:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume in early December, as the utilities complete the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.



Update as of 11/27:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Bridge crews will work a bit later than usual on December 2nd (weather permitting) to place concrete on deck two. Instead of finishing by 5 PM, the crews expect to finish between 6 PM and 8 PM.
  2. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  3. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  4. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  5. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  6. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  7. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.