Three week look-ahead 2/19 - 3/12
Below is your three week look-ahead for 2/19 - 3/12:
Update as of 3/12/21:
Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.
*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.
- Paving operations begin March 15 on the west end of the corridor between Eastridge Church and 247th PL SE (7 am – 5 pm).
- Expect delays up to 30-minutes during paving operations. Please plan accordingly.
- Duration – approximately 3 weeks.
Update as of 3/4/21:
Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.
*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.
- Paving is scheduled to begin March 15, weather permitting.
- PSE Gas Crews will complete trench work near bridge by March 8, then continue with installation under the bridge while paving is underway.
- Bridge barrier placement continues.
- Remaining areas of sidewalk, curb and gutter continues.
- Roundabout stamped concrete truck aprons are poured.
- Fencing will begin this week.
- Landscaping – topsoil placement ongoing and planting to begin soon.
|
|
|
Update as of 2/25/21:
Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.
*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.
- Bridge traffic barrier pour – first section has cured, and forms have been stripped. Work continues on remaining sections.
- Moment slabs supporting traffic barriers at the bridge approaches are completed. Sidewalks are now being formed atop these.
- Sidewalk grading underway in remaining areas.
- PSE Gas crews continue to install gas main under the bridge.
- Roundabouts – prepping for curb installation and truck aprons.
- Landscaping – installing topsoil behind sidewalks
- Fence installation beginning soon.
Update as of 2/18/21:
Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.
*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.
- Bridge barrier pour scheduled this week on south side of bridge.
- Moment slab rebar is being installed now at bridge approach, and the last segment will soon be poured.
- PSE Gas continues to install utilities under the bridge.
- Curb installation at splitter island and median islands underway.
- Roundabout truck aprons at 242nd and SE Klahanie Drive are being constructed.
- Roundabout landscape preparation is underway.