Three Week Look-Ahead 3/12 - 4/2

Below is your three week look-ahead from 3/12 - 4/2:

Update as of 4/2

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
  2. Remaining finish paving on the other side of project is planned for next dry weather.
  3. Utilities will be raising access lids in finished paved areas.
  4. Final bridge barrier section is nearly done.
  5. Guardrail and fence installation are underway.
  6. Topsoil and plants will be placed in roadway areas.


Update as of 3/26

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
  2. Remaining finish paving on the other side of project is planned for next dry weather.
  3. Utilities will be raising access lids in finished paved areas.
  4. Final bridge barrier section is nearly done.
  5. Guardrail and fence installation are underway.
  6. Topsoil and plants will be placed in roadway areas.


Update as of 3/16

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving is expected to be completed by end of the week.
  2. Final overlay paving is scheduled to begin next week but forecasted rain will likely postpone that until dry weather.
  3. If we see dry days next week, pavers will be working 7 am – 5 pm, so please plan accordingly for traffic delays up to 30-minutes.
  4. Concrete work continues at private driveways, and remaining bridge barriers, sidewalks and curb and gutters.
  5. Mailbox preparation work is beginning for final locations.
  6. Utility work continues under the bridge and at a few other locations.


Update as of 3/12

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Paving operations begin March 15 on the west end of the corridor between Eastridge Church and 247th PL SE (7 am – 5 pm).
  2. Expect delays up to 30-minutes during paving operations. Please plan accordingly.
  3. Duration – approximately 3 weeks.