Three week look-ahead 4/23 - 5/14

Below is your three week look-ahead from 4/23 - 5/14:

Update as of 5/14

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 5/7

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.


Update as of 4/30

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 4/23

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 PM on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 AM - 5:00 PM, Saturday work hours: 9:00 AM - 6:00 PM