Three-week look ahead 6/12 - 7/3

about 2 months ago

Below is your three week look-ahead for 6/12 - 7/3

Update as of 7/3:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk around the intersection will be replaced in July. The work will include relocating existing ramps and placement of new concrete and curb in around the Roundabout to better improve access for pedestrians to the crossing locations.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Also concrete curb and sidewalk placement is expected to begin.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. For more information and project updates, please visit the project portal on Connect Sammamish.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Update as of 6/19:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk around the intersection will be replaced in July. The work will include relocating existing ramps and placement of new concrete and curb in around the Roundabout to better improve access for pedestrians to the crossing locations.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Also concrete curb and sidewalk placement is expected to begin.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. For more information and project updates, please visit the project portal on Connect Sammamish.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Update as of 6/12:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. For more information and project updates, please visit the project portal on Connect Sammamish.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.


Share on Facebook Share on Twitter Share on Linkedin Email this link