Three Week Look-Ahead 7/24 - 8/14

27 Jul 2020

Below is your three week look-ahead for 7/24 - 8/14

Update as of 8/14:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor performing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor is working to complete the top beams to the substructure in preparation of the girder installation. The girders for the bridge are being delivered and installed during the week of August 24th. Girder installation will be occurring during the night time hours of August 24-August 28.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 8/7:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection are currently on schedule to start the second week of August.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor has completed the columns for each of the bridge sections and are working on the top cross beams. The girders for the bridge are expected to be delivered and installed at the end of August.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/31

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection are currently on schedule to start the second week of August.
  • Construction of the bridge is underway and on schedule to complete in December. The contractor has completed the columns for each of the bridge sections and are working on the top cross beams. The girders for the bridge are expected to be delivered and installed at the end of August.
  • Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/24:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection will be made at the end of July/early August. The new street lights are expected to be installed and operational by the end of July.
  • Construction of the bridge in underway. The contractor has completed the columns for each of the bridge sections. The contractor is currently working on the pile caps and the access road for the girder delivery. The girders are expected to begin delivery in 2 weeks.
  • Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement will continue through July. The contractor will continue to work in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is expected to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.