Issaquah Fall City Road Phase 1 Construction Updates

Share on Facebook Share on Twitter Share on Linkedin Email this link


This Project Page features a rolling three week look-ahead keeping you up-to-date on the projects progress. For more information on the project click here.

Scroll down or click here for current updates!

Issaquah Fall City Road - Detour Route. Starting on Monday, April 20th, the roadway closure will be between 245th Lane SE and Klahanie Blvd.

What and Where:

This project will widen Issaquah Fall City Road to four lanes, between 242nd Ave SE and Klahanie Dr SE. The additional lanes along with roundabouts at 242nd, 247th, and Klahanie Drive will improve traffic flow and reduce commute times on this highly-congested roadway.


When:

Road Closure: April 13th, 2020 to December 2020 (between 247th and Klahanie Dr SE) with reopening early January 2021

Estimated End of Construction: August 2021


Work Hours:

While the school closures are in place due to COVID-19, construction hours have been extended from 7 am - 5:00 pm

Monday - Friday: 9:30 am - 3:30 pm

During road closure M-F: 7 am - 8 pm (between 247th and Klahanie Dr SE)

Optional Saturday work: 9 am - 6 pm



Why:

SE Issaquah-Fall City Road is a vital connection route to residents of the City of Sammamish and surrounding communities. This project will double the existing two-lane section, to a four-lane section, and promotes the City’s goal of complete streets by including bike lanes, sidewalks, landscaping, and a protected student crossing at Pacific Cascade Middle School. A bridge located between 247th and Klahanie Drive will raise the roadway to improve safety and meet federal driver stopping sight distance requirements. North Fork Issaquah Creek will be removed from a culvert underneath the roadway into a stream channel spanned by the bridge.

For additional information click here!


This Project Page features a rolling three week look-ahead keeping you up-to-date on the projects progress. For more information on the project click here.

Scroll down or click here for current updates!

Issaquah Fall City Road - Detour Route. Starting on Monday, April 20th, the roadway closure will be between 245th Lane SE and Klahanie Blvd.

What and Where:

This project will widen Issaquah Fall City Road to four lanes, between 242nd Ave SE and Klahanie Dr SE. The additional lanes along with roundabouts at 242nd, 247th, and Klahanie Drive will improve traffic flow and reduce commute times on this highly-congested roadway.


When:

Road Closure: April 13th, 2020 to December 2020 (between 247th and Klahanie Dr SE) with reopening early January 2021

Estimated End of Construction: August 2021


Work Hours:

While the school closures are in place due to COVID-19, construction hours have been extended from 7 am - 5:00 pm

Monday - Friday: 9:30 am - 3:30 pm

During road closure M-F: 7 am - 8 pm (between 247th and Klahanie Dr SE)

Optional Saturday work: 9 am - 6 pm



Why:

SE Issaquah-Fall City Road is a vital connection route to residents of the City of Sammamish and surrounding communities. This project will double the existing two-lane section, to a four-lane section, and promotes the City’s goal of complete streets by including bike lanes, sidewalks, landscaping, and a protected student crossing at Pacific Cascade Middle School. A bridge located between 247th and Klahanie Drive will raise the roadway to improve safety and meet federal driver stopping sight distance requirements. North Fork Issaquah Creek will be removed from a culvert underneath the roadway into a stream channel spanned by the bridge.

For additional information click here!

  • Three Week Look-Ahead 4/17/20 - 5/8/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    24 Apr 2020
    supporting image

    Below is your three week look-ahead for 4/17 - 5/8

    Update as of 4/29/20:

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled.
    • Construction of the bridge has begun. So far, 6 of the 12 drilled underground shafts have been completed. Six more remain, then they will start building the above-ground work. The area is closed to the public.
    • Paving between 242nd and 247th Ave. SE is complete. Traffic has been shifted to the south side of the roadway.Work has started along the north half of the roadway in this area.
    • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

    Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

    Work hours are 8 a.m. to 5 p.m.

    CLOSURE NOTICE: Issaquah Fall City Road is closed for construction.

    • Local access will be maintained during the closure.
    • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.
    • For more information and project updates please visit the project portal on Connect Sammamish.


    Update as of 4/24/20:

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled.
    • Construction of the bridge has begun. So far, two of the drilled underground shafts have been completed. Ten more remain, then they will start building the above-ground work. The area is closed to the public.
    • Paving between 242nd and 247th Ave. SE is complete. Traffic is expected to be shifted to the south side of the roadway within the next two weeks.
    • The contractor will continue to work along the south side of the intersection of 247th Ave. SE near the middle school.

    Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    Update as of 4/17/20:

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Remaining work is expected to be completed on Monday, April 20th.
    • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
    • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving started on Friday, April 17 and is scheduled to be completed during the week of April 20th.
    • Starting Monday, April 20th, the bridge between 247th Ave SE and Klahanie Dr SE will begin. The drillers will be mobilizing on site and start drilling the concrete bridge columns. The area will be fenced off from the public.

    Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    Work hours are 8 a.m. to 5 p.m.

    CLOSURE NOTICE:

    Issaquah Fall City Road closed for construction.

    • Local access will be maintained during the closure.
    • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.
  • Three Week Look-Ahead 3/27/20-4/17/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    02 Apr 2020
    supporting image

    Below is your three week look-ahead for 3/27-4/17

    Update as of 4/17/20:

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Remaining work is expected to be completed on Monday, April 20th.
    • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
    • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving started on Friday, April 17 and is scheduled to be completed during the week of April 20th.
    • Starting Monday, April 20th, the bridge between 247th Ave SE and Klahanie Dr SE will begin. The drillers will be mobilizing on site and start drilling the concrete bridge columns. The area will be fenced off from the public.

    Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    Work hours are 8 a.m. to 5 p.m.

    CLOSURE NOTICE:

    Issaquah Fall City Road closed for construction.

    • Local access will be maintained during the closure.
    • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.

    Update as of 4/10/20:

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
    • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving is anticipated to occur during the week of April 13th, after which the traffic will be shifted to the south half.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    Update as of 4/3/20:

    • The contractor will be working on the Samm Plat waterline between 242nd Ave. SE and 247th Ave. SE. There will be a one-lane closure and a uniformed police officer at the 247th intersection this Monday, Tuesday, and Thursday.
    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Dr SE.
    • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving is anticipated to occur during the week of April 13th, after which the traffic will be shifted to the south half.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    Update as of 4/2/20:

    Starting on Monday, April 13th, 2020, Issaquah Fall City Road will be closed for construction.

    • During the week of April 13th through April 18, the road will be closed between 245th Lane SE and Klahanie Dr SE for roadway grading and shifting of the roadway access in front of Pacific Cascade Middle School.
    • Local access will be maintained during the closure.
    • The section between 245th Lane SE and 247th Place SE will reopen by the end of the day on April 18th, weather permitting.
    • Starting on Monday, April 20th, the roadway closure will be between 247th Place SE and Klahanie Blvd. This closure is expected to last through December 2020.
  • Three Week Look-Ahead 3/6/20-3/27/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    16 Mar 2020
    supporting image


    Below is your three week look-ahead for 3/6/20-3/27/20


    Update as of 3/27/20

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
    • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
    • Drainage installation continues at and around 245th and 247th.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    DATES

    Estimated dates for the ROAD CLOSURE are April 13, 2020, to December 31, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.


    Update as of 3/13/20

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
    • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
    • Drainage installation continues at and around 245th and 247th.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

    Update as of 3/6/20

    • Puget Sound Energy (PSE) will be working this Saturday, 3/7, from 9 a.m. to 6 p.m. along the south side of Issaquah-Fall City Road between 247th and Klahanie Blvd. They will be trimming trees to help set new power poles.
    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
      • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
      • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
    • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
    • Drainage installation continues at and around 245th.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road(External link),may result in shorter drive times.

    DATES

    • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
    • August 2021 - END CONSTRUCTION

  • Three Week Look-Ahead 2/18/20-3/10/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    26 Feb 2020
    supporting image

    Below is your three week look-ahead for 2/18-3/10

    Update as of 3/6/20

    • Puget Sound Energy (PSE) will be working this Saturday, 3/7, from 9 a.m. to 6 p.m. along the south side of Issaquah-Fall City Road between 247th and Klahanie Blvd. They will be trimming trees to help set new power poles.
    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
      • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
      • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
    • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
    • Drainage installation continues at and around 245th.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road,may result in shorter drive times.

    DATES

    • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
    • August 2021 - END CONSTRUCTION

    Update as of 2/28/20

    • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
    • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
    • Puget Sound Energy (PSE) Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
      • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
      • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
    • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
    • Drainage installation continues at and around 245th.
    • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road,may result in shorter drive times.

    DATES

    • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
    • August 2021 - END CONSTRUCTION

    Update as of 2/21/20

    The layout for the temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St./& E Beaver Lake Dr. SE has been completed. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed in the near future.

    Work is currently occurring primarily in front of Pacific Cascade Middle School (PCMS):

    • Through 3/27/20, PSE Electric, Comcast, Century Link, & Verizon are relocating to a joint utility trench
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines to allow the bridge construction to begin
    • Storm drainage installation continues
    • Construction continues on the new student walkway leading up to the front entrance of PCMS
    • A buried roadway section in the southern shoulder of Issaquah-Fall City Road will be dug up and removed

    Please note that during peak delays, using the project detour route, Issaquah-Beaver Lake Road to Issaquah-Pine Lake Road, may result in shorter drive times.


    Update as of 2/20/20

    Next Monday (2/24/20), single lane closures along Issaquah-Fall City Road will continue to occur for the installation of utilities.

    Update as of 2/18:

    The layout for the temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St./& E Beaver Lake Dr. SE has been completed. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed in the near future.

    Work is currently occurring primarily in front of Pacific Cascade Middle School (PCMS):

    • Through 3/27/20, PSE Electric, Comcast, Century Link, & Verizon are relocating to a joint utility trench
    • PSE Electric, Comcast, & Century Link will relocate existing poles and lines to allow the bridge construction to begin
    • Storm drainage installation continues
    • Construction continues on the new student walkway leading up to the front entrance of PCMS
    • A buried roadway section in the southern shoulder of Issaquah-Fall City Road will be dug up and removed

    Please note that during peak delays, using the project detour route, Issaquah-Beaver Lake Road to Issaquah-Pine Lake Road, may result in shorter drive times.


  • Three Week Look-Ahead 2/11/20-3/3/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    18 Feb 2020
    supporting image

    Update as of 2/18/20:

    Traffic Alert! On Thursday (2/20/20) between the hours of 9am-3pm, traffic will be restricted at the temporary roundabout intersection of Issaquah Beaver Lake Road and 256th Ave/West Beaver Lake Drive with flaggers. The contractor will be restricting the roundabout to only one leg access at a time. There will be flaggers at each of the four approaching legs to the intersection to help guide traffic through and around the location of construction. Next Monday, (2/24/20) single lane closures along Issaquah Fall City Road will continue to occur for the installation of utilities.





    Update as of 2/13/20:

    NEW Issaquah-Fall City Road Closure FAQs, with answers from our stormwater experts to the questions, "The road is still flooded. Why isn’t the water going down faster?", "What is the City doing to fix this? Can you pump the water somewhere?", "How long will the road remain flooded/closed?", and "How often are we going to see flooding events like this?"
    Click HERE to read about the road closure and see some FAQ's



    Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 2/11/20:


    2/11/20

    The Contractor for the Issaquah-Fall City Road project is taking advantage of the break in the weather to construct the roundabout at the intersection of Issaquah Beaver Lake Road and 256th Ave SE beginning today, Tuesday, February 11.

    The work has been planned and signed for a while, but the weather has delayed work up to this point. The contractor will be placing the paint striping and signage, and using orange barrels and cones until the final concrete curbs are installed over the existing asphalt roadway. The concrete work can occur with light rains and is planned to be completed by this weekend.

    The contractor will be working in the roadway between the hours of 9:30 am and 3:00 pm to account for school traffic at the neighboring middle school. Please expect flaggers during the hours of construction. Until the roundabout is complete, please follow the posted stop signs that have been used while the flooding of Issaquah-Fall City Road has occurred.

    We know there's been a lot of change at this intersection over the last week, and we thank you for using care and patience as you drive. Challenger Elementary and Beaver Lake Middle are walking schools, so please be mindful of children in the area. This roundabout will be a change for them too, so please be aware that the children might not be as aware of their surroundings as they usually are.

    If you have any questions please, contact the project manager, Sam Park, at 425-295-0538.

    Issaquah-Fall City Road (IFCR) 2/7/20

    Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times

    Work is currently occurring primarily in front of Pacific Cascade Middle School (PCMS), on the south side of the roadway:

    • PSE Gas is increasing the depth of their high pressure gas line located beneath IFCR
    • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench
    • Utilities are finalizing plans to relocate existing poles and lines to allow the bridge construction to begin
    • Storm drainage installation is continuing on the project
    • Construction continues on the new student walkway and wall leading up to the front entrance of PCMS
    • Bridge Column Rebar Cages are being built by steel fabricators and detailers off-site
    • Construction on the temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave SE/E Beaver Lake Dr. is expected to begin on Tuesday, Feb. 11.


  • Three Week Look-Ahead 1/22/20-2/12/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    22 Jan 2020
    supporting image

    Update as of 2/6/20:

    Heads up for later this week: Issaquah-Fall City Road, in the area in front of Pacific Cascade Middle School, will have one lane closed from Wednesday, February 5, through Monday, February 10, so that the general contractor can install storm drainage pipe.

    Traffic will be down to a single lane with flaggers between the work hours of 9:30 a.m. to 3:30 p.m.

    Though there is a chance that the contractor will complete this work by Friday, please be prepared for the work to go through Monday the 10th.



    Update as of 1/23/20:
    • During peak delays, using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times
    • Current items of work:
      • The initial roadway lowering has been completed on the south side of the road in front of PCMS
      • PSE Gas, PSE Electric, Comcast, Century Link, & Verizon are relocating utilities in this lowered section of the road
      • Storm drainage installation is continuing
      • Construction of the pedestrian path and the retaining wall leading to the front entrance of PCMS
      • The temporary roundabout at SE Issaquah-Beaver Lake Rd/256th Ave SE/E Beaver Lk Dr is pending, and is dry weather dependent for striping




    On Wednesday, January 21, a PSE subcontractor will allowed to begin work at 9:00 am, rather than at the regular start time of 9:30 am. This is to allow time for the connection of an upsized 6-inch gas line for Puget Sound Energy. This is the third, and final, tie-in required on the project.



    Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 1/22/19:
    • Please be prepared for additional delays as utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link).
    • Using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times during peak delays.
    • Project work is primarily in front of Pacific Cascade Middle School (PCMS)
    • Storm drainage installation has begun in the center of the roadway
    • By January 23, the south side of the road will be lowered by 5 feet to remove the existing "hump"
    • Utilities will be installing a PSE gas line and a joint utility trench once the road is lowered
    • Work continues on the new pedestrian path and retaining wall leading to the PCMS front entrance
    • The temporary roundabout at SE Issaquah Beaver Lake Rd./256th Ave./East Beaver Lake Dr. is pending, dependent on dry weather for striping
    Detour Route Map link (includes mitigation measure locations)
  • Three Week Look-Ahead 1/10/20-1/31/20

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    10 Jan 2020
    supporting image


    Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 1/10/19:

    • Please be prepared for additional delays as Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
    • During peak delays, using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times.
    • Project work is occurring primarily in front of Pacific Cascade Middle School (PCMS)
    • Storm drainage installation has begun in the center of the roadway.
    • By January 20th, the south side of the road will be lowered by 5-feet to remove the existing "hump"
    • Work continues on the new pedestrian path and retaining wall that leads up to the front entrance of PCMS
    Detour Route Map link (includes mitigation measure locations)
  • Three Week Look-Ahead 12/20/19

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    20 Dec 2019
    supporting image



    Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 12/20/19:

    • UPDATE: Please be prepared for additional delays as Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
    • The two KLAHANIE development signs will be demo'd soon. Replacement signs will be designed and installed by the Klahanie Homeowners Assoc
    • The Pacific Cascade Middle School (PCMS) sign will be removed. A replacement design and location will be coordinated directly with PCMS and ISD
    • Grading and drainage structure installation are some of the next items of work for the project

    • Detour Route Map link (includes mitigation measure locations)

    You need to be signed in to add your comment.

    comment
    Submitting your comment
    Cancel
  • Three Week Look-Ahead 12/3/19

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    04 Dec 2019
    supporting image

    Revised 12/4/19*

      Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 12/3/19:
      • UPDATE: Please be prepared for additional delays as vital Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
      • Using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times
      • Construct Stormwater facilities
      • Clear project vegetation in right of way
      • Prep for construction of a Temporary Roundabout at 256th (E Beaver Lake Dr) & SE Issaquah-Beaver Lake Road
      • Please note: The Pacific Cascade Middle School (PCMS) Sign will be removed soon. A replacement design and location is being coordinated directly with PCMS and ISD. Thank you!
      Detour Route Map link (includes mitigation measure locations)

      You need to be signed in to add your comment.

      comment
      Submitting your comment
      Cancel
    • Three Week Look-Ahead 11/5/19

      Share on Facebook Share on Twitter Share on Linkedin Email this link
      04 Dec 2019
      supporting image


        Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 11/5/19:
        • Install Stormwater pipes near the Eastridge church entrance
        • Relocate Utilities (PSE Gas, PSE Electric, Comcast, Century Link, Williams)
        • Prepare the hill in front of the school for a pedestrian walkway, stairs, and block wall
        • Clear project vegetation in right of way
        • Preparation at 256th (E Beaver Lake Dr) & SE Issaquah-Beaver Lake Road for the construction of the Temporary Roundabout
        • Please note: The Pacific Cascade Middle School (PCMS) Sign will be removed soon. A replacement design and location is being coordinated directly with PCMS and ISD. Thank you!
        • Detour Route Map link (includes mitigation measure locations)

        You need to be signed in to add your comment.

        comment
        Submitting your comment
        Cancel