Issaquah Fall City Road Phase 1 Construction Updates

Share on Facebook Share on Twitter Share on Linkedin Email this link


This Project Page features a rolling three week look-ahead keeping you up-to-date on the projects progress. For more information on the project click here.

Scroll down or click here for current updates!


What and Where:

This project will widen Issaquah Fall City Road to four lanes, between 242nd Ave SE and Klahanie Dr SE. The additional lanes along with roundabouts at 242nd, 247th, and Klahanie Drive will improve traffic flow and reduce commute times on this highly-congested roadway.


When:

Estimated End of Construction: August 2021


Work Hours:

While the school closures are in place due to COVID-19, construction hours have been extended from 7 am - 5:00 pm

Monday - Friday: 9:30 am - 3:30 pm

Optional Saturday work: 9 am - 6 pm



Why:

SE Issaquah-Fall City Road is a vital connection route to residents of the City of Sammamish and surrounding communities. This project will double the existing two-lane section, to a four-lane section, and promotes the City’s goal of complete streets by including bike lanes, sidewalks, landscaping, and a protected student crossing at Pacific Cascade Middle School. A bridge located between 247th and Klahanie Drive will raise the roadway to improve safety and meet federal driver stopping sight distance requirements. North Fork Issaquah Creek will be removed from a culvert underneath the roadway into a stream channel spanned by the bridge.

For additional information click here!




This Project Page features a rolling three week look-ahead keeping you up-to-date on the projects progress. For more information on the project click here.

Scroll down or click here for current updates!


What and Where:

This project will widen Issaquah Fall City Road to four lanes, between 242nd Ave SE and Klahanie Dr SE. The additional lanes along with roundabouts at 242nd, 247th, and Klahanie Drive will improve traffic flow and reduce commute times on this highly-congested roadway.


When:

Estimated End of Construction: August 2021


Work Hours:

While the school closures are in place due to COVID-19, construction hours have been extended from 7 am - 5:00 pm

Monday - Friday: 9:30 am - 3:30 pm

Optional Saturday work: 9 am - 6 pm



Why:

SE Issaquah-Fall City Road is a vital connection route to residents of the City of Sammamish and surrounding communities. This project will double the existing two-lane section, to a four-lane section, and promotes the City’s goal of complete streets by including bike lanes, sidewalks, landscaping, and a protected student crossing at Pacific Cascade Middle School. A bridge located between 247th and Klahanie Drive will raise the roadway to improve safety and meet federal driver stopping sight distance requirements. North Fork Issaquah Creek will be removed from a culvert underneath the roadway into a stream channel spanned by the bridge.

For additional information click here!



  • Three Week Look-Ahead 11/5/19

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image


      Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 11/5/19:
      • Install Stormwater pipes near the Eastridge church entrance
      • Relocate Utilities (PSE Gas, PSE Electric, Comcast, Century Link, Williams)
      • Prepare the hill in front of the school for a pedestrian walkway, stairs, and block wall
      • Clear project vegetation in right of way
      • Preparation at 256th (E Beaver Lake Dr) & SE Issaquah-Beaver Lake Road for the construction of the Temporary Roundabout
      • Please note: The Pacific Cascade Middle School (PCMS) Sign will be removed soon. A replacement design and location is being coordinated directly with PCMS and ISD. Thank you!
      • Detour Route Map link (includes mitigation measure locations)